News

October 20, 2016

Come to our Open House

August 26, 2016

Construction Week 26

Entre-Prises Climbing Walls​ crews finished the central climbing walls, and so we bid Bogdan and both Kamils pożegnanie as they flew home for some brief R&R […]
August 22, 2016

Construction Week 25

Entre-Prises crews worked hard to build out more of our climbing walls this week, finishing up most of their work from the previous week. On Monday […]
August 17, 2016

Construction Week 24

Entre-Prises crews turned piles of steel and plywood into climbing walls, and now we look like a climbing gym. By the end of the week, the […]
August 4, 2016

Construction Week 23

Wow, what a week. The Entre-Prises crew started paneling the climbing walls, and they look fantastic. On Tuesday a second crew from Entre-Prises showed up, put […]
July 29, 2016

Construction Week 22

It was a full house this week with a huge crew arriving from Holsinger to hang sheetrock. With a crew of up to 19 they rapidly […]