Construction Week 13

Construction Week 13

This week Evergreen put up a ton of roofing. Additional steel went up to support the metal wall panels, and you’ll see a few subcontractors preparing the mezzanine deck for the next week’s concrete pour. We found a little extra footage for the preceding Friday lying around, so you can watch French Concrete continue to pack up their forms. Unfortunately, we had some trouble this week keeping the camera powered, and we didn’t get any footage for the end of the week!

The time-lapse in this video is roughly 30 minutes of real-time per second of video. YouTube will let you change the playback speed if you want to see things more slowly or quickly. If you’ve got the bandwidth, you can also boost the resolution all the way up to 4K! Just click on the gear icon.

The next video should be a good one, including some great footage from our site superintendent of the mezzanine deck being poured.

– Brandon