Construction Week 10

Monday was a weather day (aka mud day), but Evergreen was able to make great progress during the rest of the week. Most of the rest […]
May 12, 2016

Construction Week 11

It was another week of variable weather (and beautiful cloud formations), but the crew worked around and often right through it all. Evergreen put up the […]
May 17, 2016

Climbing walls are in production

Today may be a rain day for construction in Fort Collins, but three states over in the high desert of Oregon, the team at Entre-Prises is […]
May 23, 2016

Construction Week 12

The dance of the boom lifts continued as Evergreen put up girts, purlins, framed openings, and a lot of roofing. The roof work progressed north to […]
May 27, 2016

Construction Week 13

This week Evergreen put up a ton of roofing. Additional steel went up to support the metal wall panels, and you’ll see a few subcontractors preparing […]
May 31, 2016

Construction Week 14

Evergreen continued putting up wall hat channel and roofing over the south and east sides of the building. At ground level Tipton and and High Point […]