July 5, 2016

Construction Week 18

The dance of the construction lifts continued with major interior work. Holsinger framed most of the north end of the building, turning a cavernous space into […]
July 7, 2016

Construction Week 19

It was another busy week on site, with ongoing interior and exterior work and new site work for the parking lot. To prepare the site, a […]
July 12, 2016

Construction Week 20

This week saw some real progress on our parking lot, with some grading and the first concrete pours for the curb and gutter. Detail work continued […]
July 14, 2016

Construction Week 21

The first crew from Entre-Prises arrived early this week, just ahead of the first shipment of climbing walls that came in on Friday. They wasted no […]
July 29, 2016

Construction Week 22

It was a full house this week with a huge crew arriving from Holsinger to hang sheetrock. With a crew of up to 19 they rapidly […]
August 4, 2016

Construction Week 23

Wow, what a week. The Entre-Prises crew started paneling the climbing walls, and they look fantastic. On Tuesday a second crew from Entre-Prises showed up, put […]