March 2, 2016

Formal Ground Breaking

As you may have noticed in The Coloradoan, yesterday was our formal groundbreaking! Brinkman brought out the gold shovels, and we all had a great time […]
March 7, 2016

Construction Week 3

There was quite a lot of activity during our third week of construction. On Monday Dunrite wrapped up excavation for the building structure and with Northern […]
March 16, 2016

Construction Week 4

This week was all about concrete! French Concrete finished forming, positioning rebar, and pouring the interior footing pads that will support the large columns of the […]
March 24, 2016

Construction Week 5

This week (Mar 14 – 19) French Concrete poured concrete for the foundation that supports the building walls and pilasters. You can see that most of […]
March 30, 2016

Construction Week 6

Snow and concrete were the highlights of this last week, which don’t make a great combination. Still, we were able to pour more of our foundation. […]
April 6, 2016

Construction Week 7

This last week saw almost all of the remaining concrete work for the building foundation. You’ll see that the concrete pump was out there on Tuesday […]